Progress Summary
St Aubins Town Square
- Completion of landscaping, planting and irrigation
- Practical completion of St Aubins Square with the main area opened to the public
Block 2 – West
- Completion of communication pit upgrade works
- Completion of Ausgrid power upgrade works
- Completion of water meter installation
- Completion of streetlight conduits and footings
- Completion of planter drainage in medians
- Continuing construction of landscape walls
- Continuing construction of median island kerb
- Construction of pram ramps
- Irrigation conduit install
- Commencement of footpaths on side streets
- TfNSW pavement slab rectification works
Block 1 – West
- Completion of Ausgrid conduit install
- Completion of available Telstra pit adjustments
- Construction of base course replacement
- Water meter installation
- Construction of planter drainage and electrical in medians
- Construction of landscaping walls
- Irrigation conduit install
- TfNSW pavement slab rectification works
- Construction of median island kerb
Next period’s planned activity summary
St Aubins Town Square
- Installation of street lighting and concrete
- Removal of Ausgrid street lighting
Block 2 – West
- Commencement of footpath construction
- Construction of median islands
- TCS works
Block 1 – West
- Construction of median islands
- Continuing construction of landscape walls
- Construction of pram ramps
- Ausgrid connection works (cut over planned for Sunday, 26 November 2023)