Progress Summary

St Aubins Town Square

  • Completion of landscaping, planting and irrigation
  • Practical completion of St Aubins Square with the main area opened to the public

Block 2 – West

  • Completion of communication pit upgrade works
  • Completion of Ausgrid power upgrade works
  • Completion of water meter installation
  • Completion of streetlight conduits and footings
  • Completion of planter drainage in medians
  • Continuing construction of landscape walls
  • Continuing construction of median island kerb
  • Construction of pram ramps
  • Irrigation conduit install
  • Commencement of footpaths on side streets
  • TfNSW pavement slab rectification works

 

Block 1 – West

  • Completion of Ausgrid conduit install
  • Completion of available Telstra pit adjustments
  • Construction of base course replacement
  • Water meter installation
  • Construction of planter drainage and electrical in medians
  • Construction of landscaping walls
  • Irrigation conduit install
  • TfNSW pavement slab rectification works
  • Construction of median island kerb

 

Next period’s planned activity summary

St Aubins Town Square

  • Installation of street lighting and concrete
  • Removal of Ausgrid street lighting


Block 2 – West

  • Commencement of footpath construction
  • Construction of median islands
  • TCS works


Block 1 – West

  • Construction of median islands
  • Continuing construction of landscape walls
  • Construction of pram ramps
  • Ausgrid connection works (cut over planned for Sunday, 26 November 2023)